The Ohio State University at Marion


Progress of Third Floor Renovations

June 15: In order as shown: north faculty office suite framed in ready for drywall, north hall, west hall looking south when you come off the elevator, new flex classroom, south hall in faculty suite, typical faculty office with window, student lounge, inside the media production room looking back at the control room.


May 18: Pictures #1 and #2 shows the new south faculty office suite walls framed in. Picture #3 shows a standard new faculty office area with a window and picture #4 show the east hallway looking from south to north. The faculty/staff lounge would be half way down the hall on the right and there is a new window at the north end of the hall.


May 8: Third floor, former chemistry lab, men's and women's restrooms

Former chemistry lab

Former chemistry lab

restroom

restroom

restroom

restroom


May 8: Third floor, former physics, geology labs and elevator

Former physics and geology labs

Former physics and geology labs

elevator

elevator


April 30: The floor tile and adhesive has been removed from the south side of third floor and all is cleaned up. Also, on the south side windows are started to be roughed in. This is all happening during the night.


Check back for updates in the near future.